On contracting and legal basis of activity of business entities (670-I-son) · Date: 29.08.1998 · In force
In the event of late delivery, shortage of goods, non-performance of work or non-provision of services, the supplier (contractor) pays the buyer (customer) a penalty in the amount of 0.5 percent of the unfulfilled part of the obligation for each day of delay, but the total amount of penalty should not exceed 50 percent of the value of the undelivered goods, unperformed works or undelivered services. Payment of the penalty does not exempt the party that violated contractual obligations from compensation for damages caused by late delivery, shortage of goods, non-performance of work or failure to provide services.
Source of the text
National Database of Legislation of the Republic of Uzbekistan (lex.uz). Original on lex.uz: lex.uz/docs/4403244
The text is taken from lex.uz automatically and matches it in content: it is the same text, not a separate edition. It is given for educational and reference purposes and the content of the norms is not changed. It is not an official publication: for court, contracts and official answers check the current edition on lex.uz. About
About the site: NEOLEX (veoskill) is an educational project about the law of the Republic of Uzbekistan. It does not replace lex.uz; to the same texts it adds a separate address for every article, plain-word explanations, a glossary, tests and reading in three languages. Contact: Telegram @neovixar.
Cite as: Article 25. Penalties for the delay in delivery, shortage of goods, non-performance of work or failure to provide services On contracting and legal basis of activity of business entities (670-I-son). neolex.uz/en/laws/law-10872/25 (lex.uz/docs/4403244)